To adjust finishing of sewing 110 Chapter 5 QS07 (3) To select stitch length to remove (4) To execute 7-6. To change thread tension (Frame start timing) 7-6-1. Explanation on the screen 7-6-2. How to operate The following is an example that Frame Drive Start Timing is set to "270". (1) To set to main screen (2) To press F2 key while pressing SET To change this value, consult the distributor. Some operating condition could cause occurrence of fault in thread trimming and affect sewing. 0.5 24 Target number of stitches will be displayed. Are you ready? 280 Timing to start moving the frame (Value is of main shaft angle) 230 Thread tension Weak 280 Strong 2 Frame Start Timing ! CAUTION SET + F2 screen will be displayed.